Bayliss Yard Construction, Bridgend – Bayliss

Client Bayliss Recovery Ltd
Project Construction of new service yard
Completion Date 04/2010
Contract Period 33 Weeks
Value £260k

The main project consisted of the following works: –

  • Pavement widening and entrance formation onto the new plot.
  • Ground bearing yard slabs.
  • Retaining walls using precast blocks filled with tyre bails and recycled concrete provided by the Client.
  • Insitu retaining walls using tyre bails faced with wrapping mesh and C35 grade concrete complete with F2 finishing.
  • Weighbridge foundations and pit construction for a flush finish.
  • Yard drainage complete with a tyre bail storm attenuation cell and oil interceptor unit.
  • Landscaping works.

CONSTRUCTION WITH CARE