Radial Arm Stacker – Tata

Client Corus UK
Project Construction of New HAA Conveyor and Lay Down Slab. Morfa Coal Handling.
Completion Date 08/2010
Contract Period 20 Weeks
Value £1.1m

Darlow Lloyd Construction was successful with our tender bid to Design and construct a new Coke and Coal handling conveyor and storage slab.

A non-exhausted list of the civil and mechanical installations are as follows: –

  • Construction of reinforced ground bearing storage slabs, conveyor foundations and retaining walls to facilitate the design specification.
  • Fabrication, installation and commissioning of a new connecting conveyor system complete with radial stacker discharge unit.
  • Cable Trenching for Cable Diversions from Old Conveyor location and installation of New Service Ducts and Access Chambers for new Electrical Installation.
  • Installation of a new 90mm diameter MDPE Processed water supply from an existing main on site.
  • Erection of Palisade Safety Fencing at the Entrance of the HAA Radial Stacker area.
  • Installation of 2No New Oil Retaining collection sumps and Soak-aways for the proposed ground storage slabs.
  • Construction of 2No brickwork/steel transformer pens complete with associated foundations/ cable ducting and earth pile protection.
  • Landscaping works and installation of access roads and turning areas.
  • Rail Track upgrade works including new signalling cabling, transition slabs and access pathways.